Workload Tracking
Workload tracking is available to users with a Smartsheet Business or Enterprise plan....
Sheet Summary
Use the sheet summary pane to define, organize, and report information related to your work....
In your sheet summary:
Add a Text/Number field at the top of your sheet summary with a description of the legend....
Take advantage of sheet summary to display overall project metrics, tag sheets with custom metadata for better search, and more....
Use batch copy to help keep sheet summaries consistent across up to 20 sheets.
Automatically calculate budget summaries, aggregate project status and project health, and more by placing formulas in sheet summary fields....
Gantt Charts
When you switch your sheet or report to Gantt View, tasks appear as bars in a timeline....
Right-click any column header while in the Grid and Gantt views of your sheet and select Edit Project Settings....
Here are a few things to keep in mind about non-working days and holidays in Smartsheet: If you are viewing your Gantt chart in days, non-working days...
When you enable baselines, you can view the project baseline summary to see the overall project status....
Use the Dependencies functionality in Smartsheet, to automatically calculate and adjust dates as values for Durat
If you enable dependencies in the Start Date, End Date, Duration, % Complete, and Predecessors columns, you can't use formulas....
A milestones is represented by a grey diamond image in the Gantt chart, centered on the provided start time....
The Start Date for a parent is the earliest start date from all of its child rows....
Your Critical Path is the longest distance between the start and the finish dates of your project, including all the tasks and their duration, which g...
The driving path is based on predecessor relationships. You can enable it to quickly find tasks that encroach on a vital task’s start date....
The summary path helps you identify tasks that affect the end date of a parent task.