Review the basics of setting up your Gantt View.
Gantt View is one of the four ways to view your sheet in Smartsheet and offers a visual timeline of your work. Gantt charts are a staple in traditional waterfall project management but can be used anytime you want a visual representation of your schedule and the relationships between tasks.
In order to use Gantt View, you must have at least two Date columns in your sheet: a start date and an end date.
Create and work with a Gantt chart
When you switch your sheet or report to Gantt View, tasks appear as bars in a timeline. You see the duration, the start date, and the finish date of your project tasks as project sheet columns.
Apart from that, you can also track the following:
- View Dependencies and track the relationship between tasks.
- View your project's Critical Path.
- Display the % Complete of your tasks.
- Use Hierarchy to create summary rows for further organization of your projects.
Add a Gantt chart
Before you add a Gantt chart
Make sure your sheet or report has at least two Date columns.
The columns you add must represent the start date and the end date of your tasks. The length of a task bar represents the span of time between those dates. This is why you need at least two Date columns; otherwise, you cannot switch to Gantt View.
The Gantt View does not recognize Date columns with a Column Formula applied. If you need your dates to autofill rows, use the Cell Formula and Autofill features instead. You could also set up column formulas and use a report to display your Gantt chart.
To add a Gantt chart
- In the toolbar, select Gantt View to switch your view.
The chart appears to the right of your columns. There is also a divider that separates the grid columns from the Gantt chart.
To widen the display of either section:
- Hover your pointer over the divider.
- When you see the column resize pointer
, drag the divider to the right or left.
Edit your Gantt chart
- In the upper right area of the sheet, select Edit Project Settings.
- Modify the Project Settings in each tab according to your project needs:
- Dependency Settings
- Timeline Display
- Resource Management
Adjust the timeline display
In the Project Settings dialog, you can modify the units of time you see in the Gantt chart.
An easier way to do that is by using the Zoom In and Zoom Out
buttons in the toolbar.
Organize your project tasks
Use row hierarchies in Gantt charts to organize rows into sections or phases.
When you use row hierarchies, child rows display as individual task bars in the Gantt chart based on their start and end dates. If you turn on Dependencies on the sheet, parent rows reflect a summary of their child rows.
The parent row values are calculated automatically in the following columns:
- Duration
- Start Date and End date
- % Complete
You cannot modify parent values. If dependencies are off, you can change the parent row information as needed.
Other tips in editing your Gantt chart
- Configure a % Complete column in the Project Settings dialog. Any time you enter a value in this column, you see it indicated in the task bar.
- Apply color to the task bars.
Follow step-by-step instructions to adjust your timeline.
Adjust the Gantt chart timeline
The Gantt chart has four timeline zoom levels: quarter, month, week and day.
Use the Zoom In or Zoom Out icons to adjust the view to what you need.
In the Gantt chart of a Report, you can save changes to the Gantt chart timeline, and these changes appear when exported. Only Viewers do not have access to this option.
If you are a sheet Owner or Admin access, you can further configure and customize the Gantt chart's Primary and Secondary headers by modifying the Timeline Display directly in the sheet's Project Settings.