Use Scenario Planning to create what-if scenarios from your existing project sheets, then use the Timeline and Capacity views to explore different approaches.
USM Content
You must be an Admin on the workspace where you create the plan and an Admin on all project sheets you include.
Prerequisites
Scenario Planning works with existing project sheets. Your sheets must include the following before you create a plan:
- Start Date column
- End Date column
- Assigned To column - it can be a single or multi-contact column
- Allocation column (highly recommended) - If this column doesn't exist, the capacity view is generated assuming a 100% allocation for resources on tasks by default.
Optional columns that enhance your planning: Duration, Predecessor, and Phase.
Your sheets must also have Workload Tracking enabled. If it isn't already configured, the setup flow walks you through enabling it during plan creation.
Create a scenario plan
A scenario plan is the container that holds your scenarios. You build it from existing project sheets, which become the baseline for your current plan of record.
- In the left navigation bar, select +Create, then select Scenario plan. You can also create a plan from the workspace panel.
- Select the workspace where you want to create the plan, or create a new workspace.
- Select the project sheets you want to include. You can choose sheets from any workspace you have access to, as long as you're an Admin and the sheet has at least two date columns and a contact column.
You can select up to five sheets per plan.
- Select which columns that you’d like assigned as start date, end date, and assigned to. For the Allocation column, you can add a new column, leave it blank and have it default to 100% allocation for all resources, or select an existing column.
- Smartsheet enables Workload Tracking for you if you haven’t, but you can configure it prior to using Scenario Planning if you want. This confirms which columns to use for start dates, end dates, and assignments. You can optionally configure an allocation column for more precise capacity tracking.
- Wait for validation to complete. Scenario Planning checks that all projects are properly configured.
- Name your scenario plan.
- Select Create Scenarios.
Your scenario plan opens with a read-only Current plan (your baseline for comparison) and your first editable scenario.
Create additional scenarios
You can create up to three scenarios in a single plan. Each scenario starts as a copy of the latest version of your live plans. If your data is out of sync, go to your Current plan, select the three-dot menu, and then select Refresh Data. Changes in one scenario don't affect the others.
Use the + button in the top toolbar to easily create a new scenario.
Use the Timeline view
With your scenario open, you can make changes in the Timeline view:
- Shift task dates: Double-click a task bar, or use the three-dot menu, to open the Details panel on the right and edit start and end dates.
- Reassign resources: Double-click a taskbar to change who's assigned.
- Adjust allocations: Modify how much of a resource's capacity is allocated to a task.
- Add or remove tasks: Add new tasks to a project or remove existing ones.
Filter in Timeline view
Use the filter option in the toolbar to narrow the timeline to specific tasks or projects.
To filter for a specific task in the timeline view:
- Select Filter
- Select Add a filter
- Select Primary if you’ve included task names in the Primary column
- Select values from the dropdown that you want to filter by
To remove a filter, make sure to remove it from both the Timeline and Capacity views.
Your changes appear in real time on both the timeline and capacity views.
Use the Capacity view
The Capacity view shows allocation data for your resources so you can identify overallocation hotspots and build certainty in your plan.
Each cell in the capacity view corresponds to a week or month in the timeline and shows allocation data across all projects to which a resource is assigned, not just the projects in your scenario plan. This gives you a holistic view of each resource's workload.
Whenever you select a cell, the timeline view shows the corresponding tasks for the selected resource.
Use filters to customize the capacity view for more focused planning. To remove a filter, make sure to remove it from both the Timeline and Capacity views.
With Resource Management as an add-on, you can additionally plan using placeholders, roles, and disciplines.
Placeholders help you plan efficiently when you don’t have dedicated resources assigned to the work. For more details, see our help article Use placeholders in projects.
Role indicates a person's level or title within the organization (Senior, Director, Associate).
Discipline indicates the type of work a person does within the organization, most often what department they’re in (Design, Strategy, Research).
You can easily filter to view your placeholders, roles, or disciplines' capacity in the capacity view.
You can set up roles and disciplines in Resource Management. See Assign roles and disciplines for more details.
Refresh your current plan
Your scenario plan doesn't automatically sync when your live project sheets change. If you’ve updated your source projects since you created the plan, refresh to pull in the latest data from your underlying sheets.
To refresh data, go to your Current plan, select the three-dot menu, and then select Refresh Data.
When you refresh data, it updates only the data in your Current plan. Create a new scenario if you want it to reflect your latest data.
Modify settings
If you would like to add, remove, or modify your sheet selection for the plan, use the Modify sheets button in the Settings panel.
To open the panel, select the sheets button in the top toolbar or the gear icon for Settings.
Then, select the Modify sheets button to find new or different sheets to add.
To remove sheets, simply deselect them. Once you confirm your selections, the deselected sheets no longer appear.
Things to consider
- Your Current plan is read-only. You can't edit it directly. It reflects the state of your live project sheets at the time of your last refresh.
- Changes you make in a scenario don't affect your live project sheets until you apply the scenario. Learn more about how to apply a scenario.
- To compare your scenarios side by side, learn to compare scenarios.