Create Multi-Tier Projects in Smartsheet Control Center

PLANS

  • Smartsheet Advance Package

Permissions

You must be a Primary Lead in Control Center to configure multi-tier.

Create your parent projects before creating child projects. 

The Blueprint Summary sheets for each parent list only the children for that parent. 

  1. In Smartsheet Control Center, use the parent blueprint to build the new parent project. This step generates workspaces for the child projects.
  2. Use the child blueprint to create new child projects. 
  3. On the Projects Profile Data screen, select the Parent project and the Project
  4. If you didn't select a Parent Project on the Intake Settings screen, select one now.

From this point, configure your project exactly as you would any Control Center project. Learn more about configuring Control Center projects

You can also set up Control Center to automatically provision your projects. Learn more here.

 