Create Multi-Tier projects in Smartsheet Control Center

Guiding advanced users in structuring and managing complex projects within Smartsheet Control Center.

PLANS

  • Smartsheet Advance Package

Permissions

You must be a Primary Lead in Control Center to configure multi-tier.

Create your parent projects before creating child projects. 

The Blueprint Summary sheets for each parent list only the children of that parent. 

  1. In Smartsheet Control Center, use the parent blueprint to build the new parent project. This step generates workspaces for the child projects.
  2. Use the child blueprint to create new child projects. 
  3. On the Projects Profile Data screen, select the Parent project and the Project
  4. Select one now if you didn't select a Parent Project on the Intake Settings screen. 

  5. From this point, configure your project exactly like any Control Center project. Learn more about configuring Control Center projects

You can also set up Control Center to automatically provision your projects

 