Learning Track
This Help Article appears in the Project Management in Resource Management learning track. Get the most out of this learning track by starting at the beginning.
This Help Article appears in the Project Management in Resource Management learning track. Get the most out of this learning track by starting at the beginning.
Resource Management allows you to create different types of time off and to add that time off to the schedule. That way you know who's available to work on your projects— and when.
To add leave time to a person on the Schedule:
By default, new assignments, including leave, appear on the schedule at 100% allocation for one week.
Unlike Holidays and Weekends, Resource Managment does not automatically subtract leave hours from availability calculations. Hours scheduled as leave are treated just like work hours.
You may want to split assignments after you’ve added the leave.