Use baselines and critical path

Learn how to set and manage baselines in Smartsheet to track project progress and variances. Discover how to track your project’s critical path to ensure timely completion.

Set baselines on a sheet

Who can use this?

Plans:

  • Pro
  • Business
  • Enterprise

Permissions:

  • Owners 
  • Admins

Find out if this capability is included in Smartsheet Regions or Smartsheet Gov.

When you activate baselines, three non-editable columns appear on the sheet, in addition to your actual start date and end date columns:

  • Baseline Start: The date in your start date column.
  • Baseline Finish: The date in your end date column.
  • Variance: The difference between the actual end date and the baseline end date.

Only sheet Owners or Admins can create and edit baselines. Anyone else who has been shared to the sheet can view baselines.

Brandfolder Image
Screenshot hovering over the baseline, showing that the project is on track

Keep in mind:

  • You can only add one baseline to a project sheet. If multiple start date and end date columns exist, you can only associate one set of start date and end date columns with baselines.
  • You can't add a baseline to a row without specifying both a start and an end date, or to a row with a start date that precedes the end date. The cell data must also be in an acceptable date format. For example, TBD or July don't work.
  • The activity log doesn’t track historical baseline modifications, but they can be found in the cell history.
  • Baselines appear as read-only data in cells. Consequently, baselines are displayed in reports, dashboards, and other Smartsheet items, but you can’t modify them.
  • You can convert the baseline columns to date (baseline start and baseline finish) and text/number (variance) columns, and the cell data remains unchanged.

Add a baseline to your sheet

To enable baselines on your sheet:

  1. Add start date and end date columns.
  2. In Gantt view, select the Baselines button in the toolbar. 
  3. Select Add baseline. 
    1. Your baseline summary shows your current project status and the three non-editable columns appear on the sheet.
Brandfolder Image
Gif showing how to add a baseline in new gantt view

Although the Start, Finish, and Variance columns are visible in a report, baseline bars from the Gantt view don't show in either reports or dashboard widget reports. Additionally, baselines aren't displayed when you print your Gantt view.

Edit your project baseline

To edit your baseline color and name, select the Baselines button in the toolbar  Baseline. . The summary window allows you to rename your baseline and change its display color.

Brandfolder Image
Screenshot with arrow pointing to the Baselines button in new Gantt view

To remove the baseline, select the Remove baseline icon next to the baseline toggle. The columns created automatically, however, will not be removed; you must delete them manually.

Display the critical, driving, and summary paths in a sheet

Who can use this?

Plans:

  • Smartsheet
  • Pro
  • Business
  • Enterprise

Permissions:

  • Owners 
  • Admins

Find out if this capability is included in Smartsheet Regions or Smartsheet Gov.

Use paths in Gantt view to see which tasks affect your schedule:

  • Critical path: shows the tasks that determine your project’s end date. 
  • Summary path: shows the subtasks that determine a parent task’s end date.
  • Driving path: shows the tasks that determine the start date of a selected task. 

Smartsheet updates all three paths automatically as task dates and dependencies change.

The summary and driving paths are not yet available in the new Gantt view. See Compare New Gantt view and Legacy Gantt view for more details

Before configuring any path type, you must activate dependencies.

Display the critical path in a sheet

The critical path is the longest sequence of tasks (from start to finish) that must be completed on time to stay on schedule and avoid project delays. It's determined using task start dates, end dates, duration, and dependencies (task predecessors).

As task dates or inter-task dependencies change, the sheet’s critical path can be impacted. Smartsheet automatically updates and highlights the tasks on the current critical path.

Only sheet Owners or Admins can enable dependencies to display the critical path. Anyone with Editor or higher-level permissions can edit predecessors and display or hide the critical path.

Brandfolder Image
Critical path shown in Gantt view

To display the critical path in Gantt view:

  1. Ensure dependencies are enabled. Learn more about dependencies in Gantt view.
  2. In your sheet, assign each task a start date, and an end date or duration.
  3. For each task that depends on another task, assign that other task as a predecessor in the predecessor column.
  4. To show your project's critical path, select the Show Critical Path icon in the upper-right corner of the sheet. The critical path and the items along it will be highlighted in red.

    Critical path button

The critical path appears on child rows. If the rows are collapsed and you want to view the child rows, right-click the primary column and select Expand All.

If you want to show only rows on the critical path, apply a filter for that condition.


See the parent task’s critical path with the summary path

Use the summary path to identify the subtasks impacting the end date of their summary (parent) task. The summary path is a variant of the critical path. It provides a more detailed critical path for a parent task and its subtasks, rather than showing the critical path for the entire sheet. The summary path considers all child tasks within its hierarchy.

To show or hide the summary path in Gantt View:

  1. Right-click a parent task.
  2. Select Show Summary Path or Hide Summary Path.
Brandfolder Image
Show summary path option

See the driving path for specific tasks on your sheet

The driving path is based on predecessor relationships. You can enable it to identify the tasks that affect the selected task’s start date.

To show or hide the driving path in the Gantt chart:

  1. Right-click a subtask.
  2. Select Show Driving Path or Hide Driving Path.
Brandfolder Image
Show driving path option

When the driving path appears, the tasks outlined in navy blue are the ones impacting the selected row’s start date.