While it isn’t possible to merge projects in Resource Management, if you want to transfer historical time tracked from one project into another, each person could bulk enter their historical hours for the old project into the new project and specify a date in the past (i.e. August 1, 2017) when everyone should enter their historical hours to the new project.
Alternatively, you can tag projects with the same custom field or tag, so when you view the Schedule or Reports, you can filter to see data associated with all projects with that tag or custom field.